Tanker 21 Production Update #8 & #9
 
By Union Firemen
October 11, 2016
 

Update #8

This week the truck advanced to the final assembly line after having the pump house, body modules and water tank mounted on the chassis. Additional option content is in the process of being installed. Next week it should continue having content added on the final assembly line.

Update #9

This week the truck continued on the final assembly line. Additional option content is in the process of being installed. Next week it should be released to the testing phase.