Tanker 21 Production Update #7
 
By Union Firemen
September 25, 2016
 

This week the chassis continued on the chassis prep line and the pump house was set to be mounted on the chassis. The lower body modules remained in staging and the water tank had the side sheets added. Next week the truck should advance to the final assembly line after having the pump house, body modules, and water tank mounted on the chassis.