Tanker 21 Production Update #5 & #6
 
By Union Firemen
September 20, 2016
 

Update #5 - September 9, 2016

This week the chassis continued with preparations for fire service use. The pump house finished initial assembly and began the paint process. The lower body modules began having having trim and wiring harnesses installed and the water tank side sheets finished with paint. Next week the chassis should continue on the chassis prep line. The pump house should be painted and begin pump final assembly and the body should continue on the body assembly line.

Update #6 - September 16, 2016

This week the chassis continued on the chassis prep line and cab electrical content began installation. The pump house began pump final assembly and the lower body modules finished with body assembly and are in staging. Next week the chassis should continue on the chassis prep line. The pump house should continue with pump final assembly and later in the week may be mounted on the chassis. The lower body modules should remain in staging.