Tanker 21 Production Update #3 |
By Union Firemen | |
August 29, 2016 | |
This week, the chassis finished the cab painting process. The pump and pump house structure remained in staging (no photos). The lower body modules and water tank side sheets continued with the paint process. The water tank has arrived and is in staging. Next week the chassis should begin preparations for fire service use. The pump house could begin initial assembly and the lower body and side sheets should finish the paint process. |
|
| ||||||